Hetch Hetchy Water and Power reported on March 25 as follows:
Good afternoon,
Below are planned releases from HHWP facilities through April 1. An additional update will be provided next week.
For permitting and access information contact the Groveland Ranger District.
We strive to keep the user community updated on projected flows on the Tuolumne River.
Flows will briefly increase to 6,000 cfs on Wednesday in support of the Upper Tuolumne River Ecosystem Program.
Intraday powerhouse cycling is expected to continue, following similar patterns.
Stated flow rates are best estimates and are subject to change as conditions and operational constraints evolve.