| Dreamflows South Fork Feather - Little Grass Valley Draw-Down Schedule - 2007 | ||||||||||||||||||
| "I can't boat everyday, but I can always Dream" | ||||||||||||||||||
| ||||||||||||||||||
In the table that follows, each date is color-coded according to the kind of release scheduled for that day:
| Color | Meaning |
|---|---|
| No scheduled release planned for this day. | |
| Ramping up/down from Little Grass Valley Dam during the day. | |
| Scheduled release: 300 cfs from Little Grass Valley Dam all day. |
| October 2007 | ||||||
|---|---|---|---|---|---|---|
| Sun | Mon | Tue | Wed | Thu | Fri | Sat |
| 1 | 2 | 3 | 4 Ramp up | 5 300 cfs all day | 6 300 cfs all day | |
| 7 300 cfs all day | 8 300 cfs all day | 9 300 cfs all day | 10 300 cfs all day | 11 300 cfs all day | 12 300 cfs all day | 13 300 cfs all day |
| 14 300 cfs all day | 15 300 cfs all day | 16 300 cfs all day | 17 300 cfs all day | 18 Ramp down | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 28 | 29 | 30 | 31 | |||
2. The flows were due to ramp up from about 150 cfs during the day of Thursday, October 4, ending the workday at 300 cfs. The ramping rate was 20 cfs per hour.
3. The flows below Little Grass Valley Dam were due to be at 300 cfs by the morning of Friday, October 5, and to remain at that level all day, every day, through the end of Wednesday, October 17.
4. On the morning of Thursday, October 18, flows were due to start ramping down towards the minimum flow of around 10 cfs. The ramping rate was 20 cfs per hour.
| Goto: | |||||||||||||||||||||||||||||||